Description

In general the same as the corresponding process in the buffer, FEP Bu14.

SKB Number

SKB FEP Number

TS13

Main Category

Main category for FEP

Internal process

System Component

System component to which the FEP applies

Top seal

Handling

Explanation of how the FEP is treated

Intact canister, Resaturation/ "thermal" period: Neglected. Due to the distance, chemical processes in this component will have limited impact on the performance of the rest of the repository. Intact canister, Long-term after saturation and "thermal" period: Neglected. Due to the distance, chemical processes in this component will have limited impact on the performance of the rest of the repository.

References

Bibliographic references to obtain more information

SR-Site Buffer, backfill and closure process report, TR-10-47, Section(s) 2.6.3, 7.4.5