Description

Liquefaction of the backfill in tunnels and effects thereof.

SKB Number

SKB FEP Number

BfT08

Main Category

Main category for FEP

Internal process

System Component

System component to which the FEP applies

Backfill in tunnels

Handling

Explanation of how the FEP is treated

Intact canister - Resaturation/ "thermal" period. Not relevant Intact canister - Long-term after saturation and "thermal" period. Not relevant.

References

Bibliographic references to obtain more information

SR-Site Buffer, backfill and closure process report, TR-10-47, Section(s) 2.3.4, 4.3.2; SR-Site Main report, TR-11-01, Section(s) 7.4.4