Description
Mechanisms for release of colloids from the tunnel backfill.
SKB Number
SKB FEP Number
BfT16
Main Category
Main category for FEP
Internal process
System Component
System component to which the FEP applies
Backfill in tunnels
Handling
Explanation of how the FEP is treated
Intact canister - Resaturation/ "thermal" period. Neglected if total cation charge is > 4 mM. Otherwise modelled.
Intact canister - Long-term after saturation and "thermal" period. Neglected if total cation charge is > 4 mM. Otherwise modelled.
References
Bibliographic references to obtain more information
SR-Site Buffer, backfill and closure process report, TR-10-47, Section(s) 2.3.4, 4.4.8; SR-Site Main report, TR-11-01, Section(s) 7.4.4