This report is based on a study carried out by the NEA Decommissioning Cost Estimation Group (DCEG) on decommissioning cost elements, estimation practices and reporting requirements. Its findings indicate that cost methodologies need to be updated continuously using cost data from actual decommissioning projects and hence, systematic approaches need to be implemented to collect these data. The study also concludes that changes in project scope may have the greatest impact on project costs. Such changes must therefore be identified immediately and incorporated into the estimate. Finally, the report notes that more needs to be done to facilitate the comparison of estimates, for example by providing a reporting template for national estimates.
NEA (2010), Cost Estimation for Decommissioning: An International Overview of Cost Elements, Estimation Practices and Reporting Requirements, OECD Publishing, Paris