3. DESCRIPTION OF PROBLEM OR FUNCTION
ORCOST2 estimates the cost of electrical energy production from single-unit steam-electric power plants. Capital costs and operating and maintenance costs are calculated using base cost models which are included in the program for each of the following types of plants: PWR, BWR, HTGR, coal, oil, and gas. The user may select one of several input/output options for calculation of capital cost, operating and maintenance cost, levelized energy costs, fixed charge rate, annual cash flows, cumulative cash flows, and cumulative discounted cash flows. Options include the input of capital cost and/or fixed charge rate to override the normal calculations. Transmission and distribution costs are not included. Fuel costs must be input by the user.