NEA-0486 TOTEM.

TOTEM, Demand Assessment for Nuclear Power Plants and Conventional Power Plants

top ]
1. NAME OR DESIGNATION OF PROGRAM:  TOTEM-3.
top ]
2. COMPUTERS
To submit a request, click below on the link of the version you wish to order. Only liaison officers are authorised to submit online requests. Rules for requesters are available here.
Program name Package id Status Status date
TOTEM-3 NEA-0486/01 Tested 01-JUL-1977

Machines used:

Package ID Orig. computer Test computer
NEA-0486/01 IBM 370 series IBM 370 series
top ]
3. NATURE OF PHYSICAL PROBLEM SOLVED

Starting from the total electric  energy demand in a given geographical area the number and the power  of plants of various types necessary to satisfy the demand are calculated, as well as the relevant demand of fuels, both conventional and nuclear, and possibly the costs of the produced energy. The effects of some bottle necks in the nuclear fuel cycle (e.g. in the reprocessing phase) can also be considered.
top ]
4. METHODS: METHOD OF SOLUTION
top ]
5. RESTRICTIONS ON THE COMPLEXITY OF THE PROBLEM

Maximum number of plants - 10
                  years of the strategy - 61
                  load diagram points - 10
top ]
6. TYPICAL RUNNING TIME:  For the sample problem 14 sec. CPU on IBM 370/165.
top ]
7. UNUSUAL FEATURES: UNUSUAL FEATURES OF THE PROGRAM
top ]
8. RELATED OR AUXILIARY PROGRAMS: RELATED AND AUXILIARY PROGRAMS
top ]
9. STATUS
Package ID Status date Status
NEA-0486/01 01-JUL-1977 Tested at NEADB
top ]
10. REFERENCES

- F. Conti and G. Graziani:
  'TOTEM-3, A Computer Code for the Analysis of Power Station
  Installation Policies.'
  Energia Nucleare 24, 154-164 (1977).
top ]
11. MACHINE REQUIREMENTS

300 kbytes for creating the executable load module.
200 kbytes for running the load module.
Peripherals: card reader, line printer, eventually card punch.
top ]
12. PROGRAMMING LANGUAGE(S) USED
Package ID Computer language
NEA-0486/01 FORTRAN-IV
top ]
13. OPERATING SYSTEM OR MONITOR UNDER WHICH PROGRAM IS EXECUTED:  IBM/370 O.S. MVT.
top ]
14. ANY OTHER PROGRAMMING OR OPERATING INFORMATION OR RESTRICTIONS

Implementation on other computers should be straightforward.
top ]
15. NAME AND ESTABLISHMENT OF AUTHOR

      F. Conti and G. Graziani
      Commission of the European Community
      Joint Research Centre
      Ispra, Italy.
top ]
16. MATERIAL AVAILABLE
NEA-0486/01
File name File description Records
NEA0486_01.001 TOTEM-3 SOURCE F4 EBCDIC 4833
NEA0486_01.002 TOTEM-3 OVERLAY STRUCTURE 58
NEA0486_01.003 TOTEM-3 SAMPLE PROBLEM INPUT 455
NEA0486_01.004 TOTEM-3 SAMPLE PROBLEM OUTPUT 5552
NEA0486_01.005 TOTEM-3 JOB CONTROL AND INFORMATION 67
top ]
17. CATEGORIES
  • D. Depletion, Fuel Management, Cost Analysis, and Power Plant Economics

Keywords: cost, electric power, electric utilities, energy analysis, energy demand, fuels, nuclear power plants, power plants.